Project Overview

The Costo Construction team was engaged for preconstruction services including site assessment, development of the scope of work, assembling the project team and coordination of building and development permit applications. We were then engaged as General Contractor and we assembled the Registered Professionals team.

The project consisted of upgrades to the HVAC, electrical, plumbing systems. We also renewed building envelope from the new parapet up and over the rooftop and undertook structural and seismic upgrades. The parapet wall that was deemed a public safety concern was deconstructed, rebuilt and integrated with the existing 100 year old structure. The entire project was completed while the tenant remained in operation with only two days of closure over a several months long schedule.

Completed: 07/01/2020